Watkins Mill Interchange Still Early In "Engineering Phase"

State Highway Administration briefs Gaithersburg mayor and City Council on the Watkins Mill Interchange project.

Plans for the Watkins Mill Interchange project sit in a preliminary engineering phase with 30 percent of the design completed, a State Highway Administration official told the Gaithersburg mayor and City Council Monday evening.

The preliminary engineering phase is part of a process with $6.67 million in funding and could take another 18 to 24 months to complete, said Randy Gray, SHA project manager for the Watkins Mill Interchange.

The project initially received design approval in February 2002 and will eventually result in the completion of a link between the existing Watkins Mill Road segments over I-270, providing a new East-West connection for the city of Gaithersburg.

A major issue for the project — whether the full interchange will be completed or only the bridge over I-270 — is yet to be decided, Gray said.

Current funding levels are for one project, meaning "just the overpass, no ramps structure only or the full interchange" as long as it's completed at once, without any significant breaks in construction, Gray said.

Cost options for each project range from $79.6 million to $105.9 million for the bridge only and $168.5 million to $218.4 million for the full interchange.

Although it's not the most amount of money the SHA has spent on projects like the Watkins Mill Interchange, Gray said, it's on the verge of being considered a "major interchange project."

Despite the potential costs and continued longevity of the project, Council Vice President Ryan Spiegel said he firmly believes the full interchange should be completed.

"I would really like to see this move forward as one project," Spiegel said. "Even if it might take longer and be more expensive, we need to make sure [the whole interchange is completed]."

If it's not, Gray said, the bridge would be difficult to make additions to after completion, adding that construction duration would be the same for both options, but would require a larger workforce and work on all four of the project's four quadrants at once in order to build the full interchange.

The full presentation, including information about the planned stream restoration accompanying the project, can be found on the city of Gaithersburg website.

deborah carter August 29, 2012 at 02:07 PM
i think they need to relook at watkins mill high school. the traffic since school has started is terrible, they need to find another way to separate the cars and buses into the school and out too much congestion with buses, cars and kids
Bob Hydorn August 29, 2012 at 02:20 PM
Residents of the region have long awaited this bridge and interchange. The concern of the Montgomery Village Foundation and our community are the roads leading to the area. Mainly Watkins Mill Road running from Germantown to this point passes by 4 Montgomery County Public Schools, Watkins Mill High, Stedwick Elementary, Montgomery Village Middle and Watkins Mill Elementary schools. There are students of all ages walking to school along and crossing Watkins Mill Road. This bridge and interchange will increase the volume of traffic along this roadway and as well increase the risk to the students from not only Montgomery Village but the City of Gaithersburg as well that attend these schools We look forward to the traffic relief that will come to Montgomery Village Avenue, yet with a great deal of trepidation for the increase near the schools. We certainly hope the State, County and our good neighbor next door (the City of Gaithersburg) will help to insure the safety along this new thoroughfare.
Bob Hydorn August 29, 2012 at 02:25 PM
Deborah, I have said this for several years. There needs to be a second entrance off of Watkins Mill Road, possibly nearer the bottom of the hill on Watkins Mill Road, coming up behind the football stadium tying into the drop off drive where it is located today, next to the auditorium

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something
See more »